A/C Schedule Flight APU Due Date CalculationWhen running a Planning Query, the Due Date is calculated using the APU Mean Hours. Take note of the APU mean Hours and Cycles. Run a Planning Query for the highlighted aircraft.
The Due Date shows that the maintenance event will be due on 10/18/2008. The values are calculated using the APU Mean Hours and Cycles. For this S/N, the Remaining Hours is 5000hrs. The APU Mean Hours is set up as 10, therefore the maintenance event will be due in 201days. This is calculated from the last time the Time was adjusted. Go to Technical Records/Query/P/N Time Adjustment Query.
TRAX displays the P/N Time Adjustment Query Window. Enter the P/N and S/N and select the Find
|
||||||