Publication Date: 8/17/2026 Share Print

Previous Topic

Next Topic

Book Contents

Book Index

Is the item Accepted or Rejected?

ACCEPTED: If the item going through a Receiving Inspection is to be accepted, populate the Location and Bin for the part to be placed, and populate and select the necessary tabs and buttons.

REJECTED: If the item going through a Receiving Inspection is to be rejected, populate the Location and Bin to Quarantine for the part to be Unserviceable, and populate and select the necessary tabs and buttons.

 

This decision pertains to the Receiving Process.

See Also

Receiving Inspection

Is the RI for a Repair Order?

Is the Receiving Inspection for a Rental Order?

Receiving Process Complete