Is the Audit Item(s) complete?

YES: If the Audit Item is complete, set the Status to 'Closed' and populate the Closed Date.

NO: If the Audit Item is not complete, continue with the necessary actions for the Audit Following.

 

This decision pertains to the Quality Assurance Process.

See Also

Audit Creation/Following

Is the Audit Control for a Vendor?

Audit Created

Audit Following Complete