Publication Date: 8/17/2026
Share
Print
|
||||||
|
The Transfer E/C From the W/O Engineering Control window, select one or more E/Cs to be transferred by selecting the Transfer checkbox. Then click the Transfer E/C The following drop down menu appears. Select a different Work Order that this E/C will be transfered to. Only those Work Orders that the specific E/C can be transferred to will appear in the drop down selection window.
The following informational window pops up informing which E/Cs will be transfered.
Select Yes to proceed with the transfer.
The selected E/Cs are then removed from this W/O.
Notice that the selected E/Cs have been transferred to the selected Work Order.
|
||||||