Does the E/C have a Repeat Schedule?

YES: If the E/C has a Repeat Schedule, then the Repeat Number field must be populated, along with the Repeat Schedule Hours/Cycles/Days/Date, as applicable, for planning purposes. If the E/C is to be continuous, populate the Repeat Number field with 9999.

NO: If the E/C does not have a Repeat Schedule, then leave the Repeat Number and Repeat Schedule fields empty.

For more information on these fields, refer to the Engineering Control, Schedule tab.

 

This decision pertains to the Engineering Control Process.

See Also

Engineering Control, Schedule Tab Subprocess

Proceed with Creating the E/C