Engineering Control, Schedule Control Tabs SubprocessThe Engineering Control, Schedule Control Tabs are two of the more important aspects of creating an Engineering Control. From these, the user can link the created E/C to other E/Cs, either as a Parent E/C or a Child E/C. If the E/C being created is to be linked to other E/Cs as the Parent E/C, then populate the Engineering Control, Schedule Controlled By tab. If the E/C being created is to be linked to other E/Cs as the Child E/C, then populate the Engineering Control, Schedule Control tab. If the E/C being created is not to be linked to other E/Cs, then the user can Proceed with Creating the E/C. The following is the basic life cycle of an Engineering Control, Schedule Control tabs:
Once the Engineering Control, Schedule Control tabs have been populated, as needed, the user can Proceed with Creating the E/C. |
|||||||