Depending on the way a system is set up, a user may be required to update the A/C times and cycles at the aircraft effectivity level. If an aircraft has been acquired new, adjustments are not likely to be required as there will be no previous flight log details (other than test flights) from the start of the aircraft's life. The inspections will be accurately calculated. If the aircraft brought into the system accrued previous flight hours and cycles, adjustments might be needed against the E/C actuals for the E/C to forecast correctly. Note: The configuration of switch Go to Engineering/ Update/ Engineering Control Selection, find and select into the E/C. Select the A/C
You would need to know the amount of flight time between the effective date and the beginning of the flight data. If the aircraft hours were 10,000 in 2014 and 18,000 in 2017 then you will need to enter 8,000 hours in the Actuals section (hours field). Also, the important thing in this case is to make sure the effective date is changed to the date the flight logs information starts (i.e.2017).
Override Checkbox: If the Override checkbox is selected in the Engineering Effectivity Override window, the Effective Date field can be edited. Change the date as required, select the Override checkbox again to close the Effective Date, and remember to select the Save It is a good procedure to run the Planning query and check the results of the changes made to ensure that all calculations are correct. If a problem occurs where the hours appear to be grossly exaggerated, users may need to check that the effective date entered is not prior to the first aircraft log for that tail number. The Effective Date must be greater than (>) or equal to (=) the Z-Date. The Z-Date must be set for all tail numbers.
|
||||||
| Top of Page |
Download Online Help
Print
|
|||||