A/C Planning (Inventory Planner View), Inventory Planning Tab

The Inventory Planner View The Inventory Planner tab allows planners to query for parts in inventory that are linked to Defects, E/Cs, P/N E/Cs and/or P/N Controls. Requisitions can be created for part requirements from this tab..

From the A/C Planning Query window, select the Inventory Planner View. Enter all necessary search criteria, as described below, and click on the Find but_find_small button.

Additional information for relevant features can be found through the following:

 

Planning Elements:

The following information/options are available in this window:
_____________________________________________________________________________________

P/N E/C checkbox

Select this checkbox to filter by P/N E/C.

P/N Control checkbox

Select this checkbox to filter by P/N Control (i.e. TSO, REP, HYDRO).

Note: If this checkbox is selected, the system displays the PN Maintenance Control and P/N Control fields in the Planning Filters section.

_____________________________________________________________________________________

 

From To Selection:

The following information/options are available in this window:
_____________________________________________________________________________________

Location

The Location for maintenance events, inventory stores, orders, transactions, or training events. From-To range of Location codes. Select the inventory location you want to run the query for. This field must be populated in order to receive an output. This information is being pulled from the Location Master. For additional information regarding the Location, refer to the Site Button via the Settings Training Manual.

Plan Flight Hours

From-To range of Planning flight hours (number of). Enter the estimated average flight hours for the part to have a basis for the estimation of the part's due date. Please note that the due date will exclusively be based on this estimate. While the part is in inventory it does not accumulate flight hours and does not become due. Nevertheless, this is a helpful tool to determine whether to install a part or perform the E/C or P/N Control before it is installed.

Plan Flight Cycles

From-To range of Planning flight cycles (number of). Enter the estimated average flight cycles for the part as a basis for the estimation of the due date. Please note that the due date will exclusively be based on this estimate. While the part is in inventory it does not accumulate flight cycles and does not become due. Nevertheless, this is a helpful tool to determine whether to install a part or perform the E/C or P/N Control before it is installed.

E/C Control

Enter the From-To E/C range for the forecast request. For additional information regarding the E/C Control, please refer to the Engineering Control, General Tab via the Engineering - E/C Training Manual.

Chapter / Section

Enter the ATA Chapter/Section range for the forecast request. For additional information, refer to ATA Specifications via the Settings Training manual.

P/N

The Part Number reference for the aircraft part. Enter the From-To part number range for the forecast request.

Include Interchangeable checkbox

Select this checkbox to include interchangeable parts in the query. If checkbox is selected, both Main and Interchangeable P/N E/Cs will appear in the query. From the Drop Down Selection window, select the P/N Interchangeable but_interchangeable_small button. The Interchangeable P/Ns are displayed. Select an Interchangeable P/N. The Interchangeable P/N will be populated in the P/N field in the A/C Planning Query window. If the checkbox is deselected, only the Main P/N E/C will appear in the query.

_____________________________________________________________________________________

 

Planning Filters:

The following information/options are available in this window:
_____________________________________________________________________________________

P/N S/N

The Serial Number for the specific serialized part. Enter the Part Number/Serial Number for the forecast request.

PN Maintenance Control

Enter the Part Number Maintenance Control for the forecast request. This specifies how the part will be controlled with regard to maintenance. The Part Maintenance Control code (i.e. Hard Time, On Condition). This is used in reporting and analysis. This information is being pulled from the P/N Master. For additional information refer to the P/N Master, Technical Engineering Tab via the Settings Training manual.

P/N Control

Enter the Part Number Control for the forecast request. For additional information regarding P/N Controls, refer to the P/N Control Button via the Settings Training manual.

E/C Category

Enter the Engineering Control Category for the forecast request. For additional information regarding the E/C Category, refer to the Engineering Control, General Tab section of the Engineering - E/C Training manual.

E/C Classification

Enter the Engineering Control Classification for the forecast request. For additional information regarding the E/C Control Classification, refer to the Engineering Control, General Tab section of the Engineering - E/C Training manual.

Sub Category

Enter the Engineering Control Classification Sub Category for the forecast request. For additional information regarding the E/C Classification and Sub Category fields, refer to the Engineering Control, General Tab via the Engineering - E/C Training manual.

E/C Status

Enter the Engineering Control Status for the forecast request. For additional information regarding these statuses refer to the Engineering Control, General Tab via the Engineering - E/C Training manual.

Capability Area

The capability area identifies where a maintenance task can be accomplished in association with the customer's internal capabilities (e.g., a particular E/C can only be accomplished during a heavy maintenance visit at a heavy maintenance capable Site). The capability area can be assigned for E/Cs, P/N Controls, and Defect Reports. However, a maintenance task with any Capability Area can be scheduled on Work Orders at Sites that have their Capability Area set to 'ALL'. The Capability Area can also be used as a filter in planning when scheduling maintenance events. For more information, refer to the Capability Area via the Planning Transaction Code Training Manual.

Planning Department drop down

The Planning Department Code to assist the Planning department in filtering and planning tasks.

Note: When a code is entered into this field, the results for that specific code will be included in the planning query as well as results registered to department: 'ALL.' For example, if department 'HANGAR' is entered in this field, all E/Cs with department 'HANGAR' will be included in the query results along with all E/Cs with department 'ALL,' since an E/C that is related to 'ALL' departments is also related to department 'HANGAR.'

Note: When Switch PLANDEPT is set to Yes, the Planning Dept and Planning Sub Dept fields become mandatory in the following windows: P/N Control, Engineering Control/ Other tab, Defect Report/ Defer tab. When set to No, the Planning Dept and Planning Sub Dept fields are not mandatory. For more information, refer to Switch PLANDEPT via the Planning Switches Training Manual.

Planning Sub Department drop down

The Planning Sub Department code to assist the Planning department in filtering and planning tasks.

Note: When a code is entered into this field, the results for that specific code will be included in the planning query as well as results registered to department: 'ALL.' For example, if department 'HANGAR' is entered in this field, all E/Cs with department 'HANGAR' will be included in the query results along with all E/Cs with department 'ALL,' since an E/C that is related to 'ALL' departments is also related to department 'HANGAR.'

Note: When Switch PLANDEPT is set to Yes, the Planning Dept and Planning Sub Dept fields become mandatory in the following windows: P/N Control, Engineering Control/ Other tab, Defect Report/ Defer tab. When set to No, the Planning Dept and Planning Sub Dept fields are not mandatory. For more information, refer to Switch PLANDEPT via the Planning Switches Training Manual.

Plan Element Due Date

The Planning query will only return planning element items that are due before the date entered in this field.

Within Hours/Cycles/Days

The Planning Query will only return maintenance events that have a Remaining Schedule that is less than or equal to the specified number of Hours/Cycles/Days.

And/Or drop down

Select 'And' to search for any Planning Elements which meet all search criteria. Select 'Or' to search for any Planning Elements which meet any search criteria. (i.e. Within Hours, Cycles and/or Days). Utilizing the 'Or' selection with the 'Within Days' functionality looks at the due date/current date, not just the remaining days of an E/C.

Spare Forecast checkbox

If checked, a P/N icon will appear next to all items in the A/C Planning Query results if they require parts from inventory in order to be accomplished. The P/N icon will appear in any of three colors to indicate the current availability of the part. Green will display if all parts required are available in inventory. Yellow will display if some, but not all parts are available in inventory. Red will display if no parts are available in inventory. If unchecked, the P/N icon will not appear.

Planning Job checkbox

Select the Planning Jobs checkbox to call on the following configuration switch:

  • PLNJOBACNO - (Activate Planning Job and set the number of task that will be done concurrently). If set to Yes, the A/C Tasks are processed simultaneously up to the number set in the Config Number field. In the case below, the Config Number is set to 8, therefore up to 8 of the A/C selected Tasks are processed in parallel. If set to No, A/C Tasks are processed separately one at a time.

    logo_11_small edited Note: This checkbox has been removed in TRAX Version 11 and all later releases.

Selecting this checkbox also places the planning job in the Planning History tab.

  • PLNHISTML - (Determine Planning History Time Limit). If set to Yes, the user can use the Config Number field to determine the limit for the Planning History records. The Config Number field is set to 1 hour. If set the No, the Planning History records will default to 8 hours and the Planning Jobs in the Planning History Tab will remain in the Planning From History tab for 8 hours.

Whether this checkbox is selected or deselected, Planning will no longer run parallel with TRAX Database Jobs, but will still run independently from TRAX.

_____________________________________________________________________________________

 

logo_11_small editedRun Multiple Planning Queries:

Users can now run multiple planning queries at the same time. This allows for more efficient planning as users do not have to wait for one job to be completed before beginning a new job.

Planning Query Enhancements

In This Section

A/C Planning (Inventory Planner View), Planning From History Tab

A/C Planning (Inventory Planner View), Schedule Job Tab

A/C Planning (Inventory Planner View) Results

A/C Planning (Inventory Planner View) Results Buttons

See Also

A/C Planning Query

A/C Planning (Cross Tab View), General Tab

A/C Planning (Detail View), General Tab

A/C Planning (Highest Assembly View), General Tab

A/C Planning (Index View), General Tab

A/C Planning (Interactive Planner View), General Tab

A/C Planning (Long Term View), General Tab

A/C Planning (Open Revision E/C's View), General Tab

A/C Planning (Part Forecast View), General Tab

Planning Query - No Records Found

Top of Page Publication Date: 8/17/2026 Share Print