Filter By Phase, via Interactive Planner Simulation

When the simulation is filtering by phases, the system is looking to allocate Man Hours to all Task Cards associated to Phase 1 before ManHours can be allocated to Phase 2, 3, 4, etc. If Man Hours can not be allocated to Phase 1, then the simulation will not be able to provide accurate results for the Labor Simulation.

In the following example, four Task Cards were created (DJ-1, DJ-2, DJ-3, and DJ-4) each with Phases associated to them.

PLAN_phase1

Skills and Man Hours were added to all of the Task Cards:

PLAN_predecessor2

All Task Cards are placed on the following E/C:

PLAN_phase4

The E/C was placed on a Work Order.

Observe the following set-up:

PLAN_phase3

 

Go to Planning/Query/A/C Planning Query.

Run the A/C Planning Query.

Select and Work Order and a task. Select the Run Simulation button.

PLAN_phase5

The following error messages appear in the Labor Simulation window:

PLAN_phase6

See Also

Run Simulation Button, via (A/C Planning) Interactive Planner, Selected Work Order Area

Filter By Predecessor, via Interactive Planner Simulation

Filter By Skill, via Interactive Planner Simulation

Include Hierarchy On Simulation checkbox, via Interactive Planner Simulation