Download Online Help
Print
|
|||||||
Sites ViewAt the bottom half of the homepage, each 'Long Term Visit' Site containing a heavy check Work Order for the Location are displayed along with basic Aircraft information and pending labor requirements. These Sites can be selected to access detailed information. The following screenshot is an example of the Sites View section of Production Control.
From this section of the homepage, each Site contains a bird's-eye-view of the Labor requirements associated to the W/O's Task Card Items along with current part, tool, and engineering indicators (see below for more information on these indicators).
The Site Details section of the homepage contains the following W/O-specific icons and information for each applicable Site: _________________________________________________________________________ Site information The blue line at the top of the subsection includes the Site name and the aircraft tail number that is located at the worksite. Users can click on the Site to access the Site's details window (see below for more information on the detail window). Progress % The percentage of completed work scheduled for that specific worksite for the day. W/O Description Under the Site and Aircraft information is the current Work Order's Description. The W/O number is listed in the details section (below). Labor Each Labor Category is listed in the middle of the Site subsection. When a W/O T/C Item is scheduled for the day that requires a Skill that is linked to one of these Skill Categories, that Skill Category will change color. The colors that these Categories change to quickly indicate the current assignment status. These at-a-glance color codes help production controllers plan worksite personnel accordingly.
The labor color codes are as follows:
Select Labor to access a pop-up window that includes the required Skills' schedule and assignment status. Days Early/Late Indicates the amount of days ahead of schedule or behind schedule, if any. If everything is on schedule, then the fields will read '0'. The days are also color-coded for quick reference.
Parts The color of this icon indicates the availability status for all required parts on the day's W/O T/Cs. The Parts icon color codes are as follows:
Tools The color of this icon indicates the availability status for all required parts on the day's W/O T/Cs. The Parts icon color codes are as follows:
Engineering The color of this icon indicates the current status of the Engineering Requests linked to the W/O. The Engineering icon color codes are as follows:
_________________________________________________________________________
For detailed information regarding a Site's W/O and tasks, click on a Site to access the details page. This detail window includes the Work Order schedule, Aircraft information, and W/O Task Card tabs (to the bottom of the window).
For more information on this window, refer to Sites View Details. |
|||||||