PLANDUE% - Planning Warning When Percent DuePlanning Warning When Percent Due Affected Window: w_ac_planning_sel
Switch Set to Yes: When set to Yes, the system defaults the Min Yield % field of a new Engineering Control to the percentage indicated in the switch's Config Number field. In Addition, the system will highlight (in yellow) the Due Date of the E/C in the planning query results for items that have surpassed the Min Yield % of their schedule.
The following Engineering Control is being created. Notice the Min Yield % field of the Schedule tab is defaulted to that of the switch’s Config Number.
Switch Set to No: When set to No, the system does not default the Min Yield % field of a new Engineering Control to the percentage indicated in the switch's Config Number field. In this scenario, the Min Yield % is entered manually by the user in the Engineering Control, Schedule tab.
The following Engineering Control is being created. Notice the Min Yield % field of the Schedule tab is not defaulted.
|
||||||