MANLLOR - Disable Lower Level and Override checkboxes if E/C is MandatoryDisable Lower Level and Override checkboxes if E/C is Mandatory Affected Window: w_engineering_eu
Switch Set to Yes: When set to Yes, the Lower Level and Ovr checkboxes of the E/C, Schedule Control tab cannot be selected for Mandatory E/Cs. A hard warning appears when saving the E/C if either of these checkboxes are selected.
The following Engineering Control has been created with a Classification of Mandatory.
Notice in the Engineering Control, Schedule Control tab, the Lower Level and Override checkboxes are selected. But then the window is saved, a hard warning appears.
Switch Set to No: When set to No, the Lower Level and Ovr checkboxes of the E/C, Schedule Control tab can be selected for Mandatory E/Cs.
The following Engineering Control has been created with a Classification of Mandatory.
Notice in the Engineering Control, Schedule Control tab, the the Lower Level or Override checkboxes can be selected for each record added. The window can be saved.
|
||||||